i-80 Gold Announces the Start of Production Mining at Archimedes Underground

All amounts are expressed in United States dollars unless otherwise stated TORONTO, Nov. 23, 2026 /CNW/ -- i-80 GOLD CORP. (NYSE: IAUX) (TSX: IAU) ("i-80 Gold", or the "Company") is pleased to announce that it has mined its first gold and commenced production

Illustrative imageIllustrative image

All amounts are expressed in United States dollars unless otherwise stated

TORONTO, Nov. 23, 2026 /CNW/ -- i-80 GOLD CORP. (NYSE: IAUX) (TSX: IAU) ("i-80 Gold", or the "Company") is pleased to announce that it has mined its first gold and commenced production mining on schedule at its Archimedes underground project ("Archimedes" or the "Project"). Archimedes is a high-grade gold project located on the Company's Ruby Hill property within the Battle Mountain-Eureka gold trend in Nevada, USA. It is the Company's second underground mine to come online.

"The start of production mining at Archimedes marks another significant step for i-80 Gold, further strengthening our track record of delivering on key development milestones," stated Paul Chawrun, Executive Vice President & Chief Operating Officer. "We are currently mining oxide and sulfide material at the Project. The oxide material is being placed on the active heap leach pad on the Ruby Hill property, while the sulfide material is being stockpiled for processing at our Lone Tree Plant next year. Our strong technical and operating teams and our underground mining contractor have enabled us to deliver on this milestone safely, on time and largely on budget."

Mr. Chawrun added, "Our focus for the Project now turns to ramping up mining rates through 2027 and stockpiling the refractory material mined in preparation for the commissioning of the Lone Tree Plant late in the year as Archimedes will be a key source of high-grade refractory material feed. Once the Lone Tree Plant is commissioned, we are targeting consolidated annual gold production of 150,000 to 200,000 ounces beginning in 2028 from the Archimedes and Granite Creek underground projects."(1)

Project Development

Production mining commenced following the scheduled completion of the surface and underground infrastructure required to begin production mining, including ventilation and escape raises. Lateral development to date totals approximately 3,600 meters. Ground conditions remain favorable, and the underground contractor continues to exceed planned productivity rates within the Project's upper 426 Zone. Construction of additional surface and underground infrastructure, such as additional ventilation raises, a permanent mine dry, and offices, will continue through 2027 to support the ramp up to planned mining rates.

Project construction commenced in September 2025 and has progressed largely in line with the capital development estimate in the March 2025 preliminary economic assessment (the "PEA"),(2) apart from the decision to expand and upgrade surface infrastructure to support the scale of future operations. Upon anticipated completion of the additional surface and underground infrastructure in 2027, total project capital is expected to be approximately $10 million higher than the $47.3 million estimated in the PEA.