Decision on KSM mine in B.C.'s northwest sent back for reconsideration

Seabridge Gold Inc. says it's in negotiations with a partner that has deep enough pockets to finish building its US$6.4 billion KSM mine project in northwest B.C. But the Toronto-headquartered company will first have to undergo a reconsideration of the 2024 de

Illustrative imageIllustrative image

Seabridge Gold Inc. says it's in negotiations with a partner that has deep enough pockets to finish building its US$6.4 billion KSM mine project in northwest B.C.

But the Toronto-headquartered company will first have to undergo a reconsideration of the 2024 decision that it had substantially begun construction and could thus continue under a 2014 environmental permit.

B.C. Supreme Court Judge Emily Burke last week quashed the province's July 2024 determination that construction work had "substantially started," and sent it back to the minister of environment to be reconsidered.

In doing so, Burke ordered that the province must "engage in deep consultation with the Tsetsaut Skii Km Lax Ha Nation," before reconsidering the initial decision.

Burke's Nov. 18 decision was a clarification of a June ruling, in which she determined that the Tsetsaut Skii Km Lax Ha had not been adequately consulted.

Seabridge is proposing to build what would be one of the world's largest gold and copper mines, in mountains some 65 kilometres from Stewart.

On Monday, Ryan Beaton, a lawyer for the nation, said the Tsetsaut Skii Km Lax Ha still dispute the "substantial start" designation, but the process will give them an opportunity for meaningful involvement in the project.

"The nation's point is: 'If you're going to approve that on land that, you know, the province now says is TSKLH territory, then you have to involve the nation in dealing with it,' " Beaton said.

That would mean measures such as being able to appoint environmental monitors for the deep tailings pond designed for the KSM mine and discussion between the province and the nation about land use in the region around the facility, Beaton said.

And if the mine goes ahead, Beaton said the nation wants a say in the kinds of projects that can go ahead in other areas of its asserted territory, "so that it can maintain at least some of its territory as usable for the nation."

Beaton explained that the Tsetsaut Skii Km Lax Ha were relegated to a lesser role in consultations over the KSM mine proposal more than a decade ago because the nation's asserted claims to the territory "were weak."

However, the nation's subsequent challenges proved its claims. And in 2021, the province issued a report that agreed the location of the KSM mine's proposed tailing facility is on the nation's territory.

"At that point, we said, 'If the decisions going forward didn't seek to reopen the past decision, then going forward, you now need to consult on the basis of your own conclusions,' " Beaton said.

Chief Darlene Simpson said in a statement that her nation isn't against "responsible resource development" but remains "deeply concerned" about the potential negative impacts from KSM's proposed nine-kilometre-long containment facility that reaches depths of up to 52 storeys.

"With yesterday's court decision, we hope the province finally understands it has to engage seriously with our concerns about such momentous effects on our territory," Simpson said.

Beaton added that the Tsetsaut Skii Km Lax Ha will also be looking for an impact and benefits agreement, similar to deals that the Nisga'a and Tahltan nations have with Seabridge.

"There should be some comparable multi-generational benefits for the TSKLH Nation as well," Beaton said.

Seabridge Gold CEO Rudi Fronk said Monday the company is willing to negotiate such an agreement, similar to deals it has with the Nisga'a and Tahltan, and "we've told them that many, many times."

"It's always been clear to us that there's five First Nation groups (including the Tsetsaut Skii Km Lax Ha) that we've been told to deal with at the project level in terms of consultation," Fronk said. "And we've taken that responsibility. (It's) important to us and we've had continuing consultation with all five groups now since 2008."

For their part, the Nisga'a and Tahltan First Nations declared in a joint statement that they support of the KSM mine and the substantial start decision, and rejected the Tsetsaut Skii Km Lax Ha claim.

"Our position is clear: the Nisga'a Nation and the Tahltan Nation do not recognize the TSKLH as holding any Aboriginal rights or title within our respective territories and we firmly reject the claims being made by TSKLH in relation to the KSM project," the statement read.

Fronk said that Seabridge has spent $300 million on infrastructure work since the 2024 decision, on top of the $400 million it had put in up to 2024, so he's confident the substantial start decision will stand.

"If the government thought we were substantially started at $400 million, they should think no different than the $700 million spend," Fronk said.

The CEO added that Seabridge is still in talks with a potential partner to take on full construction, having narrowed down its options over the past few years.

"We reported in our (third quarter) report that we're advancing our discussions with our preferred partner," Fronk said. "It's clear in our disclosure that we're down to one company, a company that we've been engaged with now for some period of time."